A lasts 2 days. B and C follow A and last 4 and 3 days. D takes 2 days and waits for both. Find early and late start/finish times, project duration, critical path and float.
A lasts 2 days. B and C follow A and last 4 and 3 days. D takes 2 days and waits for both B and C.
Find the early and late start and finish times, and the project duration.
Find the critical path and the float.
Higher Level Applied Maths · Algorithms, Optimisation & Project Scheduling · Step 8 of 8
A project's minimum duration is set by its longest dependency path, while forward and backward passes reveal each activity's timing limits.
In exam scheduling questions, distinguishing parallel work from sequential work prevents inflated completion times and incorrect float calculations.
A lasts 2 days. B and C follow A and last 4 and 3 days. D takes 2 days and waits for both B and C. Find the early and late start and finish times, and the project duration. Find the critical path and the float.