A service-time model is T=10+7n minutes, where n is the number of jobs. For n=13, calculate the predicted time and state what the output means.

A service time model is T = 10 + 7n minutes, where n is the number of jobs.

For n = 13, calculate the predicted time and state what the output means.

Read it once, slowly. Then copy it onto your page.
  • What is going on? A model gives a time T, in minutes, for a number of jobs, n.
  • What is fixed? This time there are 13 jobs.
  • What do they want? Two answers: the time, and what that number means in words. The output is the number the model gives back.
Céim

Ordinary Level Applied Maths · Mathematical Modelling · Step 7 of 8

Computing, Simulating & Interpreting

Calculate from a model while keeping track of what each input and output represents.

Why it matters

A numerical result is useful only when its units and meaning fit the original situation.

The worked example

A service time model is T = 10 + 7n minutes, where n is the number of jobs. For n = 13, calculate the predicted time and state what the output means.

How the worked example goes

  1. Read

    • What is going on? A model gives a time T, in minutes, for a number of jobs, n.
    • What is fixed? This time there are 13 jobs.
    • What do they want? Two answers: the time, and what that number means in words. The output is the number the model gives back.
  2. Understand

    • How do I picture it?
    • 1 job: 10 + 7 = 17 min. 2 jobs: 10 + 7 + 7 = 24 min.
    • The 10 min comes once, however many jobs: a setup time. Each job adds 7 min.
  3. Reduce

    • n = 13. Which is the next line? T = 10 + 7(13): The 7 min per job is multiplied by 13 jobs. The 10 min is added once.
    • What do I write?
    • Putting n = 13 into the model is called substituting. The exam word is substitute.
  4. Solve

    • Work it out.
    • T = 10 + 7(13)
    • 7 × 10 = 70, 7 × 3 = 21
  5. Check

    • Is it right?
    • Take off the setup, divide by 7 min per job